PUBlog
Now Open
Updates on the Pagoda
Union Building (PUB) at Shoreline Community College

The northwest corner and west side of
the PUB as it appeared on March 4, 2008. Opening has happened on
Wednesday, April 2nd. The new building has 52,000 square feet and costs roughly
$20 million.
Click
here to see photographs of
the demolition and construction progress
Current status of activity in the PUB:
-
After a long construction
process, we are happy to announce the PUB is now open.
Please feel free to come and check out
what the long wait has produced. Note the hours of
operation below and enjoy the food from Chartwells.
-
Initial
building hours for the PUB will be:
7:00am to 5:30pm Mon-Thursday and 7am to 4:30pm on Friday.
Building open hours will be adjusted as offices, the
deli/espresso and the bookstore become operational
-
The
cafeteria will be open**
7:30am to 5:30pm Mon-Thursday and 7:30am to 4:30pm on Friday**
**Once the deli/espresso is operational (scheduled for the end
of April) hours will be as follows:
cafeteria - 7:30am to 2:30pm Mon-Friday and the
deli/espresso - 7:30am to 7:30pm Mon-Thursday and 7:00 to 4:00pm
Friday
-
"Murphy's
Tent" (In honor of Murphy's Law) will operate on Monday, March
31st and Tuesday April 1st from 7:00 am to 1:30 pm. The
tent will be located in the main courtyard. Chartwells is
providing limited menu offerings at the tent until the PUB
opens.
Murphy's Menu
-
The building
number of the PUB will change from 900 to 9000 in order to
accommodate the three working floors of the building. The
numbering system will be 9100, 9200, and 9300 respectively.
-
Almost all
furniture has been received
and assembled, with a few pieces on backorder which will be
delivered on Monday, March 31.
-
Fire and
Building Inspections are being conducted March 27th and 28th.
Assuming a successful completion of the inspections, building
keys will be turned over to Safety & Security after the
completion of required paperwork with the City of Shoreline.
The general opening projected at this time
is Wednesday, April 2nd
-
Bookstore fixtures is
nearing completion. The bookstore will be moving later in
April
-
Matt Johnson
of
Chartwells, the
on-campus dining services manger, can be reached at extension
#6918, his email is
mjohnson4@shoreline.edu
-
Chartwells, the food service vendor
(a division of
Compass Group PLC),
is planning installation of the espresso-deli area, expected in
three to four weeks (after the building is open). We are
anticipating the installation completion to happen by the end of
April, but please stay tuned
-
The new catering menu has been
distributed to campus secretaries and is available
here (Adobe Acrobat .pdf file)
-
Moving of
student government and other offices is being coordinated
through Bob Roehl. Depending on schedules the moves will
most likely begin the 2nd or 3rd week of the Quarter
-
Interior temporary signage has been designed and
is being
fabricated, with installation expected late in the week
of March 24
Future activity of general interest:
-
The wooden
rails along the ramp to the FOSS building are temporary.
The permanent rails to match the rest of the building will be
installed as soon as possible. FOSS ramp opening soon (date to be
determined)
-
Exterior light poles will be repainted
at tops to conform to design specifications
-
South staff parking lot will be
cleaned and entirely re-striped
As of this writing, general opening
should be Wednesday, April 2nd.
Grand opening festivities
will be announced at a later date.
A note about access to the building prior
to formal occupancy:
Until the building is formally turned
over to the college, the contractor retains responsibility and
controls access to the space and the fenced perimeter. Our
contractor has been very cooperative in allowing the college access
for essential needs (e.g., telecommunications work, delivery and
assembly of furniture, work with our food service vendor in the
kitchen). Without such access, the college would have been required
to wait until after the contractor was completely finished with the
building to undertake these tasks. Prior to formal turnover
(expected late in the week of March 24), however, the college cannot
grant general access except to specific employees for specific
necessary purposes. Requests for such access should be addressed to
Sharon Wines in the Office of Administrative Services, extension
7859. Even with a request, it may not be possible to allow access on
certain days due to anticipated testing, inspections, or other
activities that would be compromised by excess traffic. We
appreciate your cooperation and are confident that college staff,
faculty, and students will find that the building is well worth the
wait.
Room numbers (for selected rooms):
|
The Ebbtide |
9101 |
|
First Floor Conference Room |
9102 |
|
Game Room |
9103 |
|
Mailing Services |
9109 |
|
Bookstore |
9114 |
|
Second Floor Conference Room A (to project south) |
9201 |
|
Second Floor Conference Room B (to project north) |
9202 |
|
Quiet Study Lounge |
9203 |
|
Quiet Dining Room |
9208 |
|
Staff and Faculty Lounge |
9212 |
|
Food Service Manager |
9213A |
|
Main Dining Room |
9215 |
|
Student Leadership Center |
9301 |
|
Multicultural Center and Women's
Center |
9302 |
|
Conference Room (in Multicultural
Center and Women's Center) |
9302B |
|
International Programs |
9303 |
|
Conference Room (in International
Programs) |
9303D |
Shoreline Community College
Pagoda Union Building (PUB) Project Team
Owner
Shoreline Community College District No. 7
16101 Greenwood Avenue North
Shoreline, Washington 98133-5696
(206) 546-4101;
www.shoreline.edu
contact: Stuart A.T.
Trippel, cpa, Acting
Vice President for Administrative Services
Owner's Project Manager
Washington State Department of General Administration
Division of Engineering and Architectural Services
General Administration Building
210 Eleventh Avenue Southwest, Room 206
Post Office Box 41012
Olympia, Washington 98504-1012
(360) 902-7272;
www.ga.wa.gov
contact: Jonathan B.
Martin, Engineer, Project Manager
Architect
Opsis Architecture llp
920 Northwest 17th Avenue
Portland, Oregon 97209-2318
(503) 525-9511;
www.opsisarch.com
contact: Jim Kalvelage,
aia, Principal
General Contractor
Berschauer Phillips Construction Company
1736 Fourth Avenue South
Seattle, Washington 98134-1512
(206) 626-0256;
www.bp-construction.com
contact: Jim Phillips,
Project Manager